1. The remaining projects that are proposed to be paid for with bond money are:
Shelton St Sidewalk: $215,000
Davie Rd Sidewalk: $650,000
Pine St Sidewalk: $625,000
2. Unfunded project:
Estes Sidewalk: $1,200,000
3. Other sidewalks are currently scheduled but are being funded with state and federal grant moneys that cannot easily be redirected to other projects (Ashe St, Bim St and Elm St sidewalks all fall in this category).
4. The Wilson Park Multi-use Path is fully funded and would begin (ie design phase) in 2010-11.
5. The Wilson Park Multi-use Path is now proposed to extend parallel to Estes to connect to Phase 1A of the Bolin Creek Greenway and that would happen as a part of the BC Greenway construction in more like 2011-12. The extended connection between these two would create a bike/ped only corridor that immediately parallels Estes Dr Ext for about 1/4 mile from Bolin Creek to a place opposite the entrance to Estes Park Apartments. The proposal includes a pedestrian-only, push-button-activated traffic light and crosswalk at the entrance to Estes Park Apartments.
So it appears that we can only afford the Estes sidewalk if we shelve both Pine Street and Davie Road - and personally, I think the Davie Road sidewalk project is also very important. Consequently last night I asked the Town staff to report back to the Board of Aldermen about other alternatives such as:
A) formalizing the bike/ped connection from Pleasant to Estes Park Apartments, and
B) building the Estes sidewalk, but only from Hillcrest Ave to North Greensboro Street.
The Board of Aldermen will then evaluate whether to reprogram some of the money listed under #1 above to pay for any improvements in the Estes area beyond the Wilson Park Multi-use Path (such as A and/or B above).
Also, the BOA will soon see a more detailed presentation on phase 1A of the Bolin creek Greenway/Wilson Park Multi-use Path.
Here's a rough sketch of these various proposed paths: